News

  • Roll Lift in action

19.02.2019

Artikel Nummer: 26421

Roll Group completes its Elba LNG project


After more than two years of work, Roll-Lift USA has completed the expansion of the LNG plant at the Elba Island Project located in Savannah GA (USA).

 

The first challenge to overcome was the low-weight limit and deteriorating condition of the only access bridge to the island. Finally, 9,300 poles and 71 process/pipe rack modules were transported by barge from the offsite fabrication facility located ten miles away along the Savannah River to the project site. 68 SPMTs and 72 lines of axle trailers were deployed.

 

Roll-Lift designed 85ft ro/ro ramps to bridge the poor ground at the project’s roll-off location and maintain the capacity required to handle the heavy loads. Roll Group specialises in transporting and lifting heavy cargo. (kd)

www.roll-group.com

 

 

 

Related news