Keflavik Int airport updates masterplan
Isavia has updated its masterplan for Keflavik International Airport, which marks the first update since the original development plan was published. The masterplan is reviewed and updated every five years to keep in line with changing circumstances and developments.
Valid until 2045, the current masterplan remains largely based on the previous development plan covering 2015 to 2040. The review allows for the provision of new areas for services and cargo transport, multi-story carparks, and special areas for storage, distribution, and production of sustainable energy sources for aircraft.
The plan is now divided into two phases, with phase 1 covering the period until 2035 based on the existing runway system, and phase 2 extending until 2045, assuming the addition of a third runway and related infrastructure. (cj)